How to install brush face guard system? Step-by-step instructions for installing the brush face access control system. In recent years, with the rapid development of biometrics technology, access control systems have evolved and traditional brushing access control has entered the era of brush face. Brush face access control has become the standard for many communities and companies. This article focuses on the installation of brush face access control systems and brushes. Face access control system wiring, take a look at the basic introduction of this article. Uuw Smart Lock China

2017-05-17_091651.jpg Uuw Smart Lock China

Brush Face Access System Installation Method Steps

First, equipment installation Uuw smart lock China

(1) Uuw smart lock China

A. Install a card reader at the door. Do not approach or touch high-frequency or strong magnetic fields (such as heavy-duty motors, monitors, etc.) within the reading sensing range, and match the grounding of the control box. Uuw Smart Lock China

B. Install the exit button at the exit. Uuw Smart Lock China

C. The electromagnetic lock is installed on the top edge of the door and door frame. Uuw Smart Lock China

D. To ensure safety and aesthetics, the controller and power box can be installed on-site or installed in weak electric wells. The advantage of installing the controller in the field is to save the use of wire rods. The controller is installed in the weak electric well to facilitate the system's future maintenance and system safety. The controller box can also be installed above the card reader near the electromagnetic lock. The specific situation can be selected according to the customer's installation. Uuw Smart Lock China

(2) Central Control Room Uuw Smart Lock China

A. The control panel and keyboard are installed on the facade wall or on the workbench. Uuw Smart Lock China

B. The alarm device is placed in a place where the alarm effect is better. Uuw Smart Lock China

C. Due to the special nature of the access control system, it is required to provide good power supply to the system. It is recommended to use UPS power to centrally supply power to the access control system. Uuw Smart Lock China

2017-05-17_091651_72x72.jpg Uuw Smart Lock China

Second, equipment debugging Uuw smart lock China

(1) After the installation of the system is completed, firstly access the access control card reader signal to the host, and then independently detect the situation of the access control reader on the road, whether there is any missing report or false alarm. After this way, there is no problem and then it is connected to another way. In this way, each path is individually detected, and all lines are connected after confirmation. Uuw Smart Lock China

(2) The management personnel can authorize according to the authority of the user. For example, some personnel can enter and leave an arbitrary place at any time. The ordinary person can only enter and leave the authorization scope within the authorization time by the authorization card. When all access points are normally turned on and turned on illegally, check whether the control center computer has a record. Uuw Smart Lock China

(3) Try to connect the controller to the central computer due to a fault or other reasons. Whether the controller can independently record the relevant information of the controlled door point. After the central computer is connected, whether all the information can be uploaded automatically, can the information be recorded? Integrity. Uuw Smart Lock China

(4) Make a good debugging record. Uuw Smart Lock China

(5) Finally fill in the completion report. Uuw Smart Lock China

Third, the pipeline installation Uuw smart lock China

(1) The wiring of the installation project shall comply with the national regulations “Construction and Acceptance Specifications for Electrical Installations” and relevant regulations and regulations issued by the State. The threading in the pipe or in the trunk shall be carried out after the construction plastering and ground works are completed. Prior to threading, the water and debris in the tube or in the conduit should be removed. Lines of different systems, different voltage levels, and different current categories should not be worn in the same tube or in the same slot in the raceway. There should be no joints or kinks in the pipe or in the raceway. Wire connectors should be soldered in the terminal box or connected by terminals. Small-section system connections can be hinged, the number of twisted turns should be more than five feet, then tinned and taped with insulating tape. Pipes passing through the deformation joints of buildings shall be compensated. The two sides of the conductors crossing the deformation joints shall be fixed with appropriate allowances. Terminals in the terminal box should be crimped or soldered with terminal strips. The terminals should have a suitable marking. Uuw Smart Lock China

(2) The access controller shall be installed securely, shall not be tilted, and shall have obvious signs. Installed on a lightweight partition wall, reinforcement measures should be taken. The cables or wires of access controllers shall be introduced. The wiring shall be neat and avoid crossover. The parts that should be fixed and fixed to the core wire and the conductors shall be marked with numbers, and the drawings shall not fade easily; the terminal board and each terminal shall be connected. Must not exceed two; cable cores and conductors should be left with not less than 20cm margin; the conductors should be bundled into bundles; after the lead-in conductors are threaded, they should be plugged in the conduits. Uuw Smart Lock China

2017-05-17_091748.jpg Uuw Smart Lock China

(3) The main power lead-in of the access controller should be directly connected with the power supply. It is forbidden to use the power plug. The main power supply should have obvious signs; the grounding of the access controller is solid and has obvious signs. Uuw Smart Lock China

(4) The route and specifications of the grounding bus in the monitoring room shall meet the design requirements. The following regulations shall be complied with during construction: The surface of the grounding busbar shall be complete, with no obvious damage and residual flux slag. The copper strip busbars shall be light and smooth with no burrs. The insulation layer shall have no age cracking phenomenon; the grounding bus shall be laid on the ground trough or cable The center of the aisle is fixed on the outside of the rack slot. The bus bar should be flat and must not be skewed or bent. The connection between the busbar and the rack or roof should be firm; the copper strip bus on the cable walkway can be fixed with screws; the copper strand busbar on the cable walkway should be tied to the crosspiece; the system's engineering lightning protection grounding installation should be Strictly follow the design requirements. Grounding installation should be carried out simultaneously with civil construction. Uuw Smart Lock China

The above is the method of installing the brush face access control system by the smart lock China Wang Xiaobo. More attention to the installation of the access control system, please pay attention to the content of this column! Uuw Smart Lock China